Quick answer: Before requesting kitchen or bathroom bids, write down what stays, what changes, the materials and quantities to price, and who handles purchasing, protection, disposal and permits. Attach drawings, photographs and a selection schedule. Give every bidder the same dated package, and require them to identify exclusions, allowances and assumptions separately.
The goal is not to tell contractors how to perform their trades. It is to define the result you want clearly enough that each contractor prices the same project.
The Federal Trade Commission recommends getting multiple written estimates that identify the work, materials, completion date and price—not automatically choosing the lowest bid. A shared scope gives you a practical way to follow that advice. (consumer.ftc.gov)
1. Define the project boundaries before choosing finishes
Start with a short project summary:
- Location: Project address and rooms included.
- Purpose: What the remodel must accomplish.
- Layout: What remains in place and what moves.
- Retained items: Cabinets, fixtures, appliances, doors or finishes to protect.
- Exclusions: Work you are deliberately leaving out.
- Occupancy: Whether the household will remain in the home.
- Budget: Your working budget, with owner purchases and reserves identified separately.
Avoid broad phrases such as “complete bathroom remodel.” Instead, name the assemblies involved: vanity, countertop, sink, faucet, toilet, bathing area, flooring, walls, lighting and ventilation.
For a kitchen, distinguish cabinet refinishing from cabinet replacement. Identify whether appliance positions, plumbing connections or wall openings will change.
Ask bidders to price optional upgrades separately. For example, make the specified cabinet replacement the base scope and request a separate alternate for an additional storage feature. Do not let one bidder quietly include the upgrade while another excludes it.
Practical check: A person who has not visited your home should be able to read the summary and explain what is—and is not—being renovated.
2. Attach drawings, photographs and a quantity schedule
Prepare an existing-layout drawing and a proposed-layout drawing. Label walls or elevations so that a scope entry can refer to a particular location without ambiguity.
Include:
- Room dimensions, openings and ceiling heights.
- Cabinet and appliance locations.
- Fixture locations and proposed relocations.
- Tile boundaries, backsplash limits and painted surfaces.
- Photographs keyed to the drawings.
- Product specification sheets for selected equipment.
Mark homeowner measurements as preliminary. Ask bidders to field-check relevant dimensions and identify discrepancies before final pricing. Assign responsibility for final ordering measurements explicitly.
Use a quantity schedule to show what needs counting or measuring:
| Work item | Quantity information to provide |
|---|---|
| Cabinets | Individual cabinet schedule, dimensions and accessories |
| Flooring | Measured area and boundaries; order quantity shown separately |
| Wall tile | Each wall’s dimensions, tile height and openings |
| Countertops | Layout, edges, backsplash and cutouts |
| Fixtures and hardware | Item counts and model references |
Ask contractors to distinguish installed quantities from purchasing quantities, including any proposed waste allowance. Do not silently add extra material yourself and then have the contractor add it again.
This level of specificity follows California CSLB guidance calling for detailed product descriptions, sizes, colors, material amounts and manufacturer model numbers. That guidance concerns California contracts, but the checklist is useful when preparing a bid package elsewhere. (web.cslb.ca.gov)
3. Write demolition, protection and disposal as separate tasks
Treat removal work as a defined part of the project, not an assumed inclusion.
For each affected area, specify:
- What must be removed.
- What must remain undamaged.
- Whether removed items are discarded, stored or returned to you.
- Who disconnects and reconnects affected equipment.
- Which adjacent surfaces need repair afterward.
- Who removes debris and provides final cleaning.
Also request a written protection plan covering access routes, retained finishes, work-area separation, daily cleanup and household access. Ask the contractor to identify whether any specialist assessment is needed before disturbing older materials. Do not treat a general demolition line as authorization for hazardous-material work.
A useful sample entry is:
Removal and retention: Remove the existing vanity, top, sink and associated hardware shown on the demolition drawing. Retain and protect the wall mirror and adjacent door trim. Include debris removal. Identify anticipated wall or floor patching separately. Qualified trades are responsible for affected service connections.
Specify who arranges any container, parking permission or disposal authorization that the location requires.
CSLB specifically advises including cleanup, debris removal and requests to save materials in the contract. Carry those decisions into the bid scope rather than negotiating them after demolition begins. (web.cslb.ca.gov)

4. Specify complete assemblies, not just visible finishes
Create a selection schedule with the manufacturer, product line, model, size, finish and supplier reference where known.
For cabinets, include the approved layout, door style, finish, end panels, fillers, trim, storage accessories and hardware. For countertops, identify the material, edge profile, backsplash treatment and cutouts.
For a bathroom, ask the proposal to identify the complete bathing-area assembly—not merely “tile shower.” Require the contractor to name the proposed substrate, waterproofing system, drain arrangement, tile, grout, sealant and enclosure, with installation following the selected systems’ instructions.
Worked example: turn a vague request into a priceable entry
Vague request:
Replace the vanity and install a new faucet.
Clearer scope:
Replace the vanity assembly at the location shown on the proposed plan. Price the cabinet, top, sink and faucet identified in the selection schedule. Include cabinet installation, countertop cutout coordination, qualified plumbing connections, hardware, adjacent surface repairs and debris removal. State exclusions. Do not substitute products without written approval.
This is a worked writing example, not a complete technical specification. Add actual selections before issuing it, or identify the unresolved purchases as allowances.
Practical check: For every visible product, ask, “What supporting materials, installation work and adjacent repairs must be included for this to be usable and finished?”

5. Use allowances only for clearly defined unresolved purchases
For your bid package, define an allowance as a stated amount included for an unresolved purchase. Do not let it stand in for an undefined portion of the project.
Require every contractor to use the same allowance schedule:
| Unresolved selection | Common allowance, USD | Purchasing responsibility | Required pricing clarification |
|---|---|---|---|
| Decorative light fixtures | Owner to set | Assign before bidding | Supply only, or installation too? |
| Cabinet hardware | Owner to set | Assign before bidding | Include tax and delivery? |
| Floor tile | Owner to set | Assign before bidding | Which order quantity is covered? |
| Faucet | Owner to set | Assign before bidding | Which accessories are included? |
These are blank planning fields, not suggested spending levels. Before requesting bids, replace them with amounts based on actual products you are considering.
For each allowance, state:
- Whether it includes tax, freight and delivery.
- Whether contractor markup applies and how it is calculated.
- Which labor and installation materials are priced elsewhere.
- How overspending and unused amounts will be reconciled.
- When the selection must be finalized.
Ask bidders to flag selections that could change installation pricing. Keep those possible changes separate from the purchase allowance.
When comparing proposals, use this reconciliation:
Quoted total − included allowances + common comparison allowances + priced missing scope
Keep any unresolved item marked unpriced rather than entering zero. This is a comparison worksheet, not a revised contractual price.
6. Assign purchasing duties and schedule dependencies
For each major purchase, name the person responsible for:
- Confirming dimensions and compatibility.
- Approving the order.
- Paying the supplier.
- Receiving and inspecting deliveries.
- Providing suitable storage.
- Reporting damage or missing components.
- Handling returns and replacements.
- Coordinating installation.
“Owner supplied” should not leave those duties unanswered.
Add a procurement schedule showing the required-on-site date, order deadline, delivery status and dependent work. Ask the contractor which materials must be received and checked before demolition begins.
Manufacturer lead times are planning inputs, not completion promises. For example, Cabinetworks Group’s table dated October 14, 2026 listed estimated total KraftMaid lead time at four to six weeks. That brand-specific estimate does not establish timing for your order, delivery address or installation. Obtain written confirmation from your supplier. (cabinetworksgroup.com)
For countertops, assign final-measurement coordination and ask the fabricator what must be installed or available before templating. Also identify who handles removal, sink connections and any temporary arrangement.
Practical check: Trace one item from selection through installation. If nobody owns a step, resolve it before bidding.
7. Separate permits, concealed conditions and owner changes
Include a permit-responsibility schedule: who confirms requirements, prepares submissions, obtains permits, pays fees, schedules inspections and supplies closeout records.
Do not assume that retaining fixture locations eliminates permits. In Portland, Oregon, the city’s residential plumbing guidance lists installing or replacing plumbing fixtures among work requiring a plumbing permit. It also requires a final inspection to close the permit. This is a local example, not a nationwide rule; confirm requirements with your own permitting authority. (portland.gov)
Keep three budget categories distinct:
- Base scope: Defined work being competitively priced.
- Allowances: Identified purchases not yet selected.
- Owner reserve: Money held for uncertainty, not automatic contractor authorization.
Discuss concealed-condition scenarios without prescribing a universal contingency percentage:
| Planning scenario | Treatment to agree before work |
|---|---|
| Opened surfaces match the agreed assumptions | Continue within the base scope |
| Localized deterioration is discovered | Document it, obtain a repair scope and price, and approve the change |
| Suspected hazardous material or a broader structural/service issue appears | Pause affected work, obtain qualified assessment and revise scope and schedule |
Ask for the notification procedure, evidence required, pricing method and schedule impact. Have the contractor explain how urgent protective work would be handled.
California CSLB requires scope or price changes to be documented in a written change order signed before the changed work begins. Elsewhere, verify applicable contract rules and agree on a written approval process. (web.cslb.ca.gov)
8. Issue one bid package and reconcile every exception
Give the package a revision date and send the same version to every bidder. Include drawings, photographs, selections, allowances, responsibilities and the requested pricing format.
Ask each contractor to return:
- A price for the defined base scope.
- Separate allowances and optional alternates.
- Explicit exclusions and assumptions.
- Unpriced or unresolved items.
- Proposed timing and procurement dependencies.
- Permit and inspection responsibilities.
- Payment milestones and written warranty terms.
- Questions or conflicts within the documents.
Share material clarifications with every bidder so all proposals reflect the same information.
Avoid these common mistakes:
- Comparing totals before scope: Match inclusions first.
- Treating blank lines as included: Request written confirmation.
- Mixing finish budgets with installed prices: Separate purchases from labor and supporting materials.
- Accepting verbal promises: Put agreed details into the documents.
- Losing the final scope at contract stage: Attach the agreed revision and schedules to the contract.
The FTC advises checking contractor licensing with state or county government and requesting proof of insurance. A detailed proposal is useful, but it is not evidence of either credential. (consumer.ftc.gov)
Your scope is ready when another bidder can identify the same work, price the same selections and clearly explain every remaining uncertainty.